Spanish Navy to Receive S-82 Narciso Monturiol Submarine in 2026

Delivery of the S-82 Narciso Monturiol to the Spanish Navy is scheduled for December 10, 2026, at Cartagena Arsenal. Navantia and the Navy will formally accept the second boat of the S-80 series during an institutional ceremony, according to Vice Admiral Alejandro Cuerda, commander of Cartagena Arsenal.

The date represents an adjustment from the initial schedule, which had placed delivery in the final week of November. The schedule changed after the general election was moved forward to November 29.

Harbor Trials and Submerged Operations

The Narciso Monturiol has completed harbor and sea trials ahead of joining the Submarine Flotilla. Testing began in October 2025 after launch and covered the platform, propulsion, navigation, and combat systems.

During the harbor phase, the main equipment was verified, the electrical systems were energized, and the batteries were installed. In February, the submarine started its three diesel generators for the first time. Built by Navantia Cartagena under MTU license, each generator produces 1,200 kilowatts.

In late June, the S-82 made its first sea sortie in Cartagena waters using its own propulsion. In late July, it conducted a static dive to periscope depth near La Algameca Naval Base to assess the behavior of the hull, ballast tanks, and the vessel’s stability.

The campaign continued with dynamic dives and submerged-navigation trials at varying depths. In September, it reached its maximum operational depth for the first time. On August 27, it also sailed alongside the S-81 Isaac Peral off Cartagena in the first joint sortie by the two submarines.

Sustainment and Armament Contracts

The planned delivery coincides with two funding authorizations tied to the S-80 program. On November 10, the Council of Ministers authorized an open-ended implementation order for modernization and evolutionary development of the submarines, with an estimated value of €2.3736 billion.

The effort is intended to maintain the operational capability of boats in service, upgrade their equipment, and ensure their sustainment, availability, and reliability throughout their service lives. A €792 million contract was also approved for the development, integration, and procurement of the NSM missile in its submarine version. Together, the two authorizations total more than €3.165 billion.

With acceptance of the S-82, the Spanish Navy will have two new-generation S-80 submarines, which are intended to progressively replace the Galerna-class boats. In early November, the S-81 Isaac Peral took part in the live-fire Sinkex 26 exercise south of the Canary Islands, where it sank the former patrol vessel Infanta Elena with a wire-guided DM2A4 heavyweight torpedo.

Navantia continues to build the S-83 Cosme García and S-84 Mateo García de los Reyes submarines in Cartagena. These two boats will incorporate the air-independent propulsion, or AIP, system from construction. The system will later be installed in the first two submarines during their major refits to extend submerged operations without requiring use of the snorkel to recharge batteries.

What do you think about this information? We invite you to leave a comment and share the article on your social media networks.

Comments must comply with ClaveDefensa’s participation rules. Failure to do so may result in removal.

Subscribe
Notify of
guest
0 Comments
Oldest
Newest Most Voted

Puede interesarte